The volume is certain; the tonnage is not
A gravel takeoff has two halves with very different reliability, and most calculators blur them together. Area times depth divided by 27 is arithmetic — it is exactly right, every time. Converting those cubic yards into tons requires a unit weight, and unit weight is a measured property of one quarry’s product on one day, determined by a laboratory test (ASTM C29). It is not a constant of nature.
So this tool reports cubic yards as the reliable figure and tons as a conversion you can see and change. The presets come from WSDOT’s published estimating table, which is genuinely authoritative for the materials it lists. What it is not is universal: gravel from a different geology, screened differently, at a different moisture content, will weigh differently. When your supplier quotes a tons-per-yard figure, theirs wins.
Truck measure versus compacted on roadway
The detail almost every gravel calculator drops is that the same material has two unit weights. WSDOT lists crushed surfacing base course at 1.48 tons per cubic yard in truck measure and 1.85 compacted on the roadway. Ballast runs 1.55 loose against 1.95 placed. The material has not changed — the air between the stones has.
This matters twice. It is why you compute tonnage against the compacted figure, because that is the volume you are actually filling. And it is why a delivery looks alarmingly large next to the area you are covering: the same tonnage occupies roughly a quarter more space loose in the truck than it will once rolled. The working below shows both numbers so nobody has to guess whether they were shorted.
What this will not tell you
It will not tell you how deep to go. Spread depth for a driveway depends on traffic loading, subgrade strength, drainage and frost, and a number pulled off a calculator page is not a substitute for a spec or a local engineer. The 4 inches the tool opens with is a starting value so the maths has something to chew on, not advice.
It also will not price pea gravel, river rock or decomposed granite from a preset, because those are landscape materials rather than DOT pay items and no authoritative table covers them. Enter your supplier’s tons per cubic yard instead. Inventing a plausible-looking average and presenting it beside genuinely sourced figures would make the sourced ones worth less.